Data-driven production scheduling and control systems are essential for manufacturing organisations to quickly adjust to the demand for a wide range of bespoke products, often within short lead times. This paper presents a self-learning framework that combines association rules and optimization techniques to create data-driven production scheduling. A new approach to predicting interruptions in the production process through association rules was implemented, using a mathematical model to sequence production activities in real or near real-time. The framework was tested in a case study of a ceramics manufacturer, updating confidence values by comparing planned values to actual values recorded during production control. It also sets a production corrective factor based on confidence value and success rate to avoid product shortages. The results were generated in just 1.25 seconds, resulting in a makespan reduction of 9% and 6% compared to two heuristics based on First-In-First-Out and Short Processing Time strategies.
A self-learning framework combining association rules and mathematical models to solve production scheduling programs
Giulio Marcucci
;
2024-01-01
Abstract
Data-driven production scheduling and control systems are essential for manufacturing organisations to quickly adjust to the demand for a wide range of bespoke products, often within short lead times. This paper presents a self-learning framework that combines association rules and optimization techniques to create data-driven production scheduling. A new approach to predicting interruptions in the production process through association rules was implemented, using a mathematical model to sequence production activities in real or near real-time. The framework was tested in a case study of a ceramics manufacturer, updating confidence values by comparing planned values to actual values recorded during production control. It also sets a production corrective factor based on confidence value and success rate to avoid product shortages. The results were generated in just 1.25 seconds, resulting in a makespan reduction of 9% and 6% compared to two heuristics based on First-In-First-Out and Short Processing Time strategies.I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.